Independent commentary to counter the left-leaning, politically correct bigotry of a majority of mainstream journalists.
  Home     Index to Topics    Useful Links      Interesting Statistics        About Us        Support us       Your Say  
 

Perth to Mandurah rail cost leaps another $100m before work starts - total may now exceed $2 billion

Martin Lehmann - 3 January 2004

When the Gallop government took over the controversial Mandurah railway project from the outgoing Liberal government, the estimated cost was $1.2billion. Costs since then have rapidly escalated. Planning minister Alannah MacTiernan revealed on 16 December another $100 million blow-out, taking the total to $1.52 billion even before work has commenced. 

Four of the State's most experienced construction experts, led by consulting chartered engineer Peter Bruechle, warned in an open letter to the government on 27 September 2003 that the city rail tunnel plan could blow out by up to $700 million, taking the total cost of the project over $2 billion. They said the plan to run the rail along the freeway, across two bridges and then under the city is fraught with financial dangers. "History shows that the cost of major tunnelling works cannot be accurately ascertained and that there are normally substantial cost overruns", they said.

Dodgy figures fail to hide misuse of taxpayer funds

Although the Gallop government has re-routed the proposed railway system and vastly increased the overall cost, the table above, taken from the South West Metropolitan Railway Master Plan (page 73) illustrates the duplicity of the planners in trying to justify the rail system over the equivalent bus system.

The planners have tried to assess the financial viability of the project by calculating its Net Present Value. This is a standard method used by planners, corporations and entrepreneurs to calculate the value of a project by adding all the estimated cash flows over the life of a project and discounting them by a certain rate to value the project in terms of today's dollars. 

The planners have used some very questionable figures for the rail option. For example they have estimated a cash flow of $519.7m for something called "User benefits". They have defined these as savings in travel time and "the benefits to passengers diverting to rail".

It looks like they plucked these figures out of the air to pump up the rail option. 

In spite of the dodgy figures, the planners arrived at the startling conclusion that while the bus option has a positive NPV of $60.2m, the rail option has a negative NPV of $64.5m.

No business operator using his own money or company director using shareholders funds would ever proceed with a project with such a large negative NPV.

I interviewed a retired senior executive from the Main Roads Western Australia. He told me two things:

  1. His planners never thought the rail option was preferable to the bus option. He believed the railway was a political decision.
  2. Travel time savings on railways are an illusion. If you are comparing train travel time with private vehicles, you have to take into account the time taken to drive or bus from your home to the railway station and to wait for the train. Then you have to count the time taken at the other end to drive or take a taxi or bus to your destination.

 

 

 
 
 
 
 
 

Copyright (c) 1998-2007 Australian News Commentary - all rights reserved